Brownfield Retrofits & As-Built Drawings
Retrofits: CapEx Optimization
Whether upgrading an existing facility or retrofitting someone else’s, brownfield sites come with the infrastructure in place.
Brownfield vs Greenfield
| Brownfield Retrofit | Greenfield Build | |
|---|---|---|
| Power | The utility service and transformers are already on site. | New utility service and transformers must be acquired, running into demand curves and wait lines. |
| Water | The water rights are usually already in place. | New water and power rights must be applied for. |
| Permits | The site is already zoned and permitted for industrial use. | New zoning, site and environmental permits are required. |
| Community | Existing facilities don’t invite scrutiny. | New projects often face public hearings and protests. |
| Site | Roads, rail and buildings are already in place. | Everything has to be built from the ground up. |
| Schedule | Operations can start within months. | It usually takes years to go from land to operation. |
Faster To Build
Brownfield projects can often be completed in 6 to 12 months, compared with 18 to 36 months for a new build.
OPSdesign, Sept 17, 2025Shorter Approvals
Clean energy projects that went through federal environmental review from 2010 to 2023 took 54 months on average.
Resources for the Future, Aug 5, 2025Less Pushback
Local opposition blocked or delayed $68 billion of U.S. data center projects from April to June 2026.
Data Center Watch, Sept 21, 2026The First Step Of Any Retrofit Is Understanding Existing Conditions
ARY goes on site, scans the facility and turns the scan into as-built drawings and models the design team can work from.
Scan The Site
ARY captures a 3D laser scan of the facility as it stands today.
Agree On The Deliverables
ARY reviews the scan with the client’s team and agrees on the drawings and models the project needs.
Deliver As-Builts
ARY delivers as-built CAD drawings, P&IDs or Revit models of what is actually there.
Retrofit And As-Built FAQ
What is a brownfield project?
A brownfield project upgrades, expands or reuses an existing industrial facility. A greenfield project is built on undeveloped land.
Does buying an existing facility count as a brownfield project?
Yes, when the buyer upgrades or expands it, and the work starts with knowing the existing conditions.
Is this the same as an EPA brownfield?
No. In environmental law, a brownfield is property where contamination may make reuse harder. On this page, brownfield means an existing facility that is being upgraded or expanded.
What is an as-built?
An as-built is a drawing or model that shows a facility the way it exists today.
What is the difference between as-built and record drawings?
Record drawings are the design drawings updated with the changes reported during construction. The as-built drawings ARY makes are measured from the facility itself, so they show what is actually there.
What is scan to BIM?
Scan to BIM turns a 3D laser scan of a facility into a Revit model of the building, equipment and piping as they stand today.
Why scan before a retrofit?
Old drawings rarely match the facility after years of changes. A scan gives designers real dimensions, so new equipment fits the first time.
What does a scan include?
Every scan includes a registered point cloud. As-built drawings and models, such as plans, P&IDs or Revit models, are made from it as the project needs.
Does ARY do the engineering?
No. ARY only does documentation. ARY gives engineers and contractors an accurate record of existing conditions to design from.